Groisman Engineering is involved in constructing the Jerusalem LRT Network since DAY 1
From beginning of construction of the Red Line corridor being a part of the SPC/EPC team, trough PM services to the JTMT (Gov.) for the Blue, Green and Purple corridors. The company covers all aspects of engineering and construction such as design, management and construction supervision
Groisman Engineering served in various positions:
- Head of OPC of the EPCDesign coordination of Depot and Substations
- Deputy construction officer for the CWE
- Supervising the construction of the CWE
- Scheduling coordination of the EPC
- Claims assitance
The first LRT project in Israel
Groisman Engineering is involved in constructing the Jerusalem LRT Network since DAY 1
From beginning of construction of the Red Line corridor being a part of the SPC/EPC team, trough PM services to the JTMT (Gov.) for the Blue, Green and Purple corridors. The company covers all aspects of engineering and construction such as design, management and construction supervision
Groisman Engineering served in various positions:
- Head of OPC of the EPCDesign coordination of Depot and Substations
- Deputy construction officer for the CWE
- Supervising the construction of the CWE
- Scheduling coordination of the EPC
- Claims assitance